Hi there,
Does anyone know how to change the datum value when producing cross sections?
changing the datum value when producing cross sections
-
- Posts: 2
- Joined: Fri May 30, 2014 11:49 am
-
- Posts: 5716
- Joined: Tue Oct 04, 2005 12:50 pm
- Location: Brisbane
- Contact:
The datum value is automatically calculated for you, based on the data being plotted, and a few parameters on the following branches of the PPF Editor:
Boxes/Centreline labels=>Common parameters
Boxes/Centreline labels=>Boxes=>Datum lines
Boxes/Centreline labels=>Centreline=>Datum lines
If you want to set a constant datum, that can be a bit tricky. See this other post for one possible idea:
http://forums.12dmodel.com/viewtopic.php?t=1060